How long does a building permit take in the Netherlands? The statutory deadlines

What the Omgevingswet and the General Administrative Law Act (Awb) say about the decision period for an omgevingsvergunning: the regular term, extension, the extended procedure and what to do if the municipality is late.

Quick answer

The law gives no "average" duration, only deadlines within which the municipality must decide. For the regular procedure the deadline is eight weeks after receipt of the application (Omgevingswet, art. 16.64 para. 1). This article deliberately sticks to what the statute says; how long your own municipality takes in practice is something only that municipality can tell you.

Regular procedure

  • The competent authority decides within eight weeks of receiving the application (Omgevingswet, art. 16.64 para. 1).
  • If the intended decision requires consent as referred to in article 16.16, the period is twelve weeks (Omgevingswet, art. 16.64 para. 1).
  • The authority may extend either period once, by at most six weeks; the extension decision must be published within the decision period (Omgevingswet, art. 16.64 para. 2).
  • If the municipality asks you to supplement the application, the decision period is suspended until the day you supplement it or the set period expires unused (Awb, art. 4:15 para. 1 under a).

Extended procedure

  • Division 3.4 of the Awb (the extended preparatory procedure) applies to activities designated by order in council, or at the request or with the consent of the applicant (Omgevingswet, art. 16.65 para. 1).
  • The draft decision is made available for inspection and anyone can submit views; that period is six weeks unless a statute sets a longer one (Awb, art. 3:16 para. 1).
  • The decision follows as soon as possible and at the latest six months after receipt of the application (Awb, art. 3:18 para. 1).
  • For a very complex or contested subject the period can be extended once by a reasonable period of at most six weeks, within eight weeks of receipt of the application (Omgevingswet, art. 16.66 para. 3 and Awb, art. 3:18 para. 2).

What if the municipality is late?

  • A permit is granted by operation of law ("van rechtswege") only if a statutory provision says so (Awb, art. 4:20a para. 1). In the text of the Omgevingswet we checked, there is no provision that a late omgevingsvergunning is granted by operation of law. Do not assume that silence from the municipality is consent.
  • If a decision on an application is not given in time, the authority forfeits a penalty payment for each day of default, for at most 42 days (Awb, art. 4:17 para. 1). You must first give written notice of default (Awb, art. 4:17 para. 3).
  • An appeal to the court against a failure to decide in time is possible without a prior objection (Awb, art. 7:1 para. 1 under f).

After the decision

  • The period for lodging an objection or appeal is six weeks (Awb, art. 6:7).
  • For a decision prepared with the extended procedure you can normally go straight to appeal, without an objection phase (Awb, art. 7:1 para. 1 under d).

Sources

All provisions were checked on the date below against the consolidated text on wetten.overheid.nl.

sulerr.nl prepares a document package for a house from the catalogue: drawings, a cost estimate with price sources and a schedule. It is an AI draft with automatic checks and has not been reviewed by a specialist; at the moment we generate new-build houses, other work is handled on request. See the sample package