Building permit refused in the Netherlands: objection, appeal and higher appeal under the Awb

What the General Administrative Law Act (Awb) says about objecting to and appealing a refused omgevingsvergunning: deadlines, the notice of objection, the decision period, interim relief and higher appeal.

Quick answer

A refusal of an omgevingsvergunning can, as a rule, first be challenged by an objection to the authority that took the decision, and then by an appeal to the administrative court (Awb, art. 7:1 para. 1). The period for lodging a notice of objection or appeal is six weeks (Awb, art. 6:7). This article describes only the rules in the Awb; it is not legal advice.

Step 1: objection

  • You object by submitting a notice of objection to the authority that took the decision (Awb, art. 6:4 para. 1).
  • The notice is signed and contains at least your name and address, the date, a description of the decision and the grounds of the objection (Awb, art. 6:5 para. 1).
  • The six-week period starts on the day after the decision was announced in the prescribed manner (Awb, art. 6:7 and art. 6:8 para. 1).
  • A document is on time if it is received before the end of the period; if sent by post it is also on time if delivered to the post before the end of the period and received no later than one week after it (Awb, art. 6:9).
  • A late notice is still not declared inadmissible only if it cannot reasonably be held that you were in default (Awb, art. 6:11). Do not count on this.
  • Before deciding on the objection, the authority gives interested parties the opportunity to be heard (Awb, art. 7:2 para. 1).

How fast must the authority decide on the objection?

  • The authority decides within six weeks of the end of the objection period, or within twelve weeks if an advisory committee has been set up (Awb, art. 7:10 para. 1).
  • The authority may postpone the decision by at most six weeks (Awb, art. 7:10 para. 3).
  • Further postponement is possible only on the conditions of art. 7:10 para. 4, for example if all interested parties agree.

Step 2: appeal to the administrative court

  • An interested party can appeal a decision to the administrative court (Awb, art. 8:1). The period is again six weeks (Awb, art. 6:7).
  • The notice of appeal is submitted to that court (Awb, art. 6:4 para. 3).
  • No prior objection is needed in the cases of art. 7:1 para. 1, for example if the decision was prepared with the extended procedure of division 3.4 (Awb, art. 7:1 para. 1 under d) or if the appeal concerns a failure to decide in time (Awb, art. 7:1 para. 1 under f).

Interim relief

  • If an objection or appeal has been lodged, the preliminary-relief judge can, on request, grant an interim measure if urgency so requires in view of the interests involved (Awb, art. 8:81 para. 1).

Higher appeal

  • An interested party and the authority can lodge a higher appeal against a district court ruling as referred to in art. 8:66 para. 1 or art. 8:67 para. 1 (Awb, art. 8:104 para. 1 under a). Some rulings cannot be appealed further (Awb, art. 8:104 para. 2).

A new application

An objection or appeal procedure is not mandatory. You can also submit an amended application. What change removes the ground for refusal is stated in the decision itself; read its reasoning first.

Sources

sulerr.nl prepares a document package for a house from the catalogue: drawings, a cost estimate with price sources and a schedule. It is an AI draft with automatic checks and has not been reviewed by a specialist; at the moment we generate new-build houses, other work is handled on request. See the sample package