Building permits in the Netherlands: where the rules sit and which deadlines apply
A short English-language map of the Dutch building permit rules: the Omgevingswet for the permit and its decision period, the Awb for objection and appeal, and the Bbl for the energy requirements of a new home.
Three texts to know
Dutch building permit rules are spread over three texts. This guide points to the relevant provisions and states only what we checked in the statute text.
- The Omgevingswet governs the omgevingsvergunning itself, including the decision period (Omgevingswet, art. 16.64).
- The General Administrative Law Act (Awb) governs objection and appeal, and the extended procedure (Awb, art. 6:7, art. 7:1 and art. 3:18).
- The Besluit bouwwerken leefomgeving (Bbl) contains the technical requirements, including the energy requirements for a new building (Bbl, art. 4.148).
Decision period
- The competent authority decides within eight weeks of receiving the application, or twelve weeks if consent as referred to in article 16.16 is required; the authority may extend this once by at most six weeks (Omgevingswet, art. 16.64 para. 1 and 2).
- In the extended procedure the decision follows at the latest six months after receipt of the application (Awb, art. 3:18 para. 1).
- Details and what to do when the authority is late are in our article on decision periods.
Objection and appeal
- The period for lodging a notice of objection or appeal is six weeks (Awb, art. 6:7).
- As a rule an objection comes before an appeal to the administrative court, with exceptions (Awb, art. 7:1 para. 1).
- Details are in our article on a refused permit.
Energy requirements for a new home
- A new building must be nearly energy neutral (Bbl, art. 4.148 para. 1).
- For a single-family home ("andere woonfunctie") with a ratio Als/Ag of at most 1.5, table 4.148A sets an energy demand of at most 55 kWh/m2/yr, primary fossil energy use of at most 30 kWh/m2/yr and a renewable share of at least 50 percent (Bbl, table 4.148A, row 1e).
- Calculations follow the standard NTA 8800 (Bbl, art. 4.149 para. 1).
- The consulted Bbl version lists several future amendments, the first on 1 January 2027, so check the current text on the date of your application (wetten.overheid.nl, consulted 22 November 2026).
What is not covered here
Whether your specific project needs a permit, and which documents your municipality wants to see, depends on the municipal omgevingsplan and the Omgevingsloket; this guide does not answer that.
Sources
- Omgevingswet (BWBR0037885), checked on 2026-11-22.
- Besluit bouwwerken leefomgeving (BWBR0041297), checked on 2026-11-22.
- Algemene wet bestuursrecht (BWBR0005537), checked on 2026-11-22.
sulerr.nl prepares a document package for a house from the catalogue: drawings, a cost estimate with price sources and a schedule. It is an AI draft with automatic checks and has not been reviewed by a specialist; at the moment we generate new-build houses, other work is handled on request. See the sample package